What Are AEP Central's TDU TDSP Delivery Charges?


 


Monthly TDSP Delivery Charges
Charge/Fee Type Amount Description
Customer Charge per month per month $3.19000 Standard customer charge per retail customer per month
Metering Charge per month per month $3.55000 Standard metering (meter-reading) charge per retail customer per month
AMS Surcharge per month $2.26000 Additional payment for the implementation of Advanced Meters in utility area
Total Monthly Charges   $9.00  
TDSP Delivery Charges Per kWh
Charge/Fee Type Amount Description
Energy Efficiency Cost Recovery Factor (EECRF) per kWh Usage $0.000504 Charge for the TDU's cost recovery of energy efficiency programs
Transmission System Charge per kWh Usage $0.00519 Charge for electricity transmission from the generating plants to electrical substations
Distribution System Charge per kWh Usage $0.01392 Charge for electricity distribution (local electric wiring)
Transition Charges (Schedule TC2 and TC3) per kWh Usage $0.00585 Charges assessed by a TDU for the costs of transition to a competitive, deregulated market. TC is zero as of 1-29-16
Nuclear Decommissioning Charge per kWh Usage $0.00002 A fee that covers the cost of safely removing a nuclear generation facility from service
Transmission Cost Recovery Factor (Rider TCRF) per kWh Usage $0.006517 A fee (or credit) that accounts for changes in wholesale transmission rates without the need of a TDU rate case
Total Charges per kWh Usage $.037663